Coleman Boulevard Improvement Project

Coleman Banner_1350x367

Facts, Two-Week Outlooks, Photo Gallery & More!

Description

The Coleman Boulevard Improvement Projects are an important infrastructure project for the Town of Mount Pleasant. This $18.2 million project is being performed by Blythe Development of Charlotte, North Carolina and is expected to be completed in October 2019. The roadway portion of the total project cost is $14.74M and the utility portion is $3.46M.

This key infrastructure project involves reconstructing Coleman Boulevard between Mill Street and Pherigo Street to create stormwater, roadway and utility upgrades. An adaptive traffic signal system will be installed along Coleman Boulevard to streamline traffic flow and transit amenities such as bus pullouts and shelters will also be installed. Additionally, the project will provide increased travel opportunities for bicycles and pedestrians, decorative street lighting, a way-finding system, landscaped medians and a vibrant activity zone between the roadway and buildings fronting the street.

Coleman Boulevard Construction Update 

November 2019

The Coleman Boulevard Project is in the final weeks of construction and motorists, pedestrians, bicyclists and business owners can now enjoy the finished product.  Asphalt paving is complete and landscaping and decorative lighting should be complete in the next few weeks. Mast arm traffic signal installations are still ongoing with the adaptive signal control and detection system currently being installed.  Once this advanced technology is installed and calibrated, motorists will see improvements to the flow of traffic on Coleman Boulevard.  

Schedule

Start Date:  September 11, 2017

Completion Date:  December 27, 2019

Motorists are advised to use caution and drive carefully through the construction zone.

Project Contact: Ed Barbee, Transportation Construction Liaison – (843) 640-2422