Shem Creek Phase III

sc phase iii

Description

This project is part of the Coleman Boulevard Revitalization Project. This is a continuation of Shem Creek Park. The project has a few different aspects to it including an independent pedestrian bridge that will span the creek making a connection with the Coleman Blvd sidewalk on the east side and the existing boardwalk on the west side, an ADA compliant ramp leading down to Tavern and Table, as well as a pocket park. This project is consistent with the Comprehensive Plan in that it increases public access to the water, enhances sense of place, increases connectivity, and prioritizes the pedestrian environment.

Status

Phase III Update: The final design for the Phase 3 to provide a pedestrian overpass is complete. The project mobilized February 11, 2019. Construction has temporarily closed the boardwalk March 11, 2019 - May 1, 2019. Check out the video made by Thomas & Hutton on the final rendering! 

Schedule

  • Conceptual Designing/ Planning: November 2016
  • Permitting: September 2017
  • Designing: January 2018
  • Mobilizing: February 2019
  • Estimate Completing: August 2019

Cost

$3,061,000 (Funding date started 7/1/2015; Fully funded by the Hospitality Recreation, Hospitality Transportation, and TIF Revenue)

Resources

Phase 3 Project Overview

View of Creek Rendering

Rendering Shem Creek Park 

Video Rendering

Project Location

Contact

Kevin Mitchell, Project Manager